California SWPPP: risk levels, QSDs and what the 2022 permit requires

In California a Qualified SWPPP Developer (QSD) must write the SWPPP, under the State Water Board's Construction General Permit, Order 2022-0057-DWQ (in effect since September 1, 2023, expiring August 31, 2028). It's uploaded to SMARTS with the NOI and the first annual fee ($511 plus $54 an acre). There's no official template; the QSD picks the format.

Updated November 13, 2026. Sources: Order 2022-0057-DWQ and its attachments, the Board's permit FAQ and the FY 2026-27 fee schedule.

The QSD and the QSP

The permit says it twice: the SWPPP and every amendment are "developed by a QSD" (Section V.A.2), and the discharger keeps a QSD from the start of the project until the Notice of Termination is approved (V.C.1). A second role, the Qualified SWPPP Practitioner (QSP), runs the site side: inspections, sampling and putting the plan into practice.

From Order 2022-0057-DWQ, Sections V.C, V.D and V.F, and Attachment B.
QSDQSP
DoesWrites and amends the SWPPP; inspects within 30 days of start, twice a year (Aug to Oct and Jan to Mar), and within 14 days of a numeric action level exceedanceInspects on site monthly and within 72 hours before a forecast qualifying storm; samples; trains delegates
Becomes one byA prerequisite such as CPESC, CPSWQ or a California landscape architect registration, then CASQA's QSD course and examA prerequisite such as CESSWI or CISEC, then CASQA's QSP course and exam
ShortcutCalifornia-licensed professional engineers and geologists can self-certify as QSD or QSP on the Board's site
Keeps it by6 hours of continuing education a year and renewal every two years

So a contractor can't write their own California SWPPP unless they're a QSD. What a contractor or owner can do is gather the facts a QSD needs, and a QSD can start from any template or draft they choose. The Board's FAQ: QSDs "may develop their own templates or use templates from other organizations, so long as they comply with the requirements of the 2022 CGP."

Risk levels

Every traditional site gets a combined Risk Level of 1, 2 or 3, which SMARTS works out from two inputs (Attachment D.1):

From Attachment D and Table 5 of the order.
Risk LevelInspectionsSampling
1Weekly, and before, during and after each qualifying stormNon-visible pollutants only, when triggered
2SameStormwater grab samples for pH and turbidity; action levels pH 6.5 to 8.5 and 250 NTU
3SameAs Risk Level 2, plus receiving water monitoring if pH leaves 6.0 to 9.0 or turbidity tops 500 NTU

A qualifying storm is a forecast of at least 50% chance of rain and 0.5 inches or more in 24 hours. Linear utility projects get Types 1, 2 and 3 instead, under Attachment E.

What a California SWPPP must include

Section IV.O.2 lists it. Compared with EPA's template, California asks for more drawings and a monitoring program:

Filing in SMARTS

  1. The QSD prepares the SWPPP, site drawings and Risk Level inputs.
  2. The Legally Responsible Person, or a Duly Authorized Representative, certifies the Permit Registration Documents in SMARTS: the NOI with the Risk Level, the drawings, the SWPPP, post-construction plans and calculations (under the permit's standards or your MS4's), and the annual fee.
  3. Coverage begins when SMARTS issues a WDID number. No work before that.
  4. Upload SWPPP amendments within 30 days, keep the plan and readable maps on site, and certify an Annual Report by September 1 for each July-to-June year.
  5. File a Notice of Termination in SMARTS when the site is stabilized. The permit applies until the Regional Water Board approves it, and the Board's FAQ says terminating is what ends the annual fee.

Fees

The annual fee under 23 CCR 2200 is $511 plus $54 per acre disturbed over the life of the project, rounded to the nearest acre, up to $11,311. The first year is paid with the NOI. From the Board's per-acre chart: 1 acre $565, 5 acres $781, 10 acres $1,051. A Small Construction Rainfall Erosivity Waiver, for 1 to 5 acres where R is under 5 for the work period, costs $200 instead.

Ways to get it done

A QSD is required, so the choice is how much of their time you pay for. QSD fees are by quote. To cut that time, some owners hand the QSD a first draft:

Fees for QSDs and what they usually include are in the SWPPP cost guide; the preparer rules in other states are in who can write a SWPPP.

Questions

Can I write my own SWPPP in California?

Only if you're a QSD. The permit requires a QSD to develop the SWPPP and every amendment. California-licensed professional engineers and geologists can self-certify; others take CASQA's course and exam after a prerequisite certification.

Does the State Water Board have a SWPPP template?

No. The Board's FAQ says it doesn't provide one, so dischargers and QSDs choose a format that meets the 2022 permit.

How much is the California construction stormwater fee?

$511 plus $54 per disturbed acre a year, capped at $11,311. The first year is paid with the NOI and later invoices follow each year while coverage lasts. A 1-acre site pays $565.

About this page

This guide is published by Winding AI, Inc., the company that makes ePlan, one of the ways to get a SWPPP drafted that this site compares. We make money when someone pays ePlan to download a document or subscribes; we earn nothing from links to agencies or other products, and links to ePlan carry a tag so ePlan can count visits from here. Every fact on this page was read from the source it links to on the date shown above.